WHY SNOWY 2.0 IS WORTH THE CLIMB
The modern history of the Snowy Mountains is defined by those unafraid to take on the hardest tasks to secure our nation’s future. The post WHY SNOWY 2.0 IS WORTH THE CLIMB appeared first on Snowy Hydro .
-
SNOWY 2.0 COST REASSESSMENT COMPLETE
The updated target cost to complete Snowy 2.0 is $22.2 billion, with an allowance for a cost scenario of $25 billion, following a comprehensive cost reassessment by principal contractor Future Generation Joint Venture. The post SNOWY 2.0 COST REASSESSMENT COMPLETE appeared first…
-
FUNDING SECURES HERE 2 HELP CHILDREN’S PROGRAM AT TURA LIBRARY
Bega Valley Shire Library has welcomed two years of funding support from Snowy Hydro to sustain its Here 2 Help Children's Program at Tura Library, ensuring migrant families in the region continue to access vital early learning and settlement services. The post FUNDING SECURES…
-
52 YEARS NOT OUT FOR LONG-SERVING LARRIKIN TONY
When Tony Werrett joined Snowy Hydro on October 14 1974, the Sydney Opera House had only just opened, black-and-white TVs were still the norm and Advance Australia Fair had just been named our national anthem. The post 52 YEARS NOT OUT FOR LONG-SERVING LARRIKIN TONY appeared…
-
CONCRETE PROGRESS AS UNDERGROUND POWER STATION STARTS TO TAKE SHAPE
Work to build Snowy 2.0’s underground power station has begun, marking a new phase of the project. The post CONCRETE PROGRESS AS UNDERGROUND POWER STATION STARTS TO TAKE SHAPE appeared first on Snowy Hydro .
-
KURRI KURRI POWER STATION UPDATE
Having completed commissioning on Kurri Kurri Power Station’s (KKPS) primary gas fuel earlier in the year, Snowy Hydro is ready to complete the final stage of commissioning using the back-up diesel fuel. The post KURRI KURRI POWER STATION UPDATE appeared first on Snowy Hydro .
-
ANAO PERFORMANCE AUDIT: DELIVERY OF SNOWY 2.0
Snowy 2.0 is our nation’s most critical energy project. Designed to operate for 150 years, it represents a generational investment in Australia’s energy sovereignty. The post ANAO PERFORMANCE AUDIT: DELIVERY OF SNOWY 2.0 appeared first on Snowy Hydro .
-
SNOWY 2.0 IS A NON-NEGOTIABLE FOR AUSTRALIA’S FUTURE ENERGY SECURITY
Independent modelling from Baringa Partners confirms Snowy 2.0 is critical to maintaining reliable electricity supply and market stability after coal-fired power stations retire. The post SNOWY 2.0 IS A NON-NEGOTIABLE FOR AUSTRALIA’S FUTURE ENERGY SECURITY appeared first on…
-
MAJOR BREAKTHROUGH ACHIEVED AS TBM MOMENTUM BUILDS
A major milestone has been reached on Snowy 2.0, with TBM Lady Eileen Hudson completing excavation of a 6-kilometre tunnel and successfully breaking through into the underground cavern complex deep in the Snowy Mountains. The post MAJOR BREAKTHROUGH ACHIEVED AS TBM MOMENTUM…
-
SNOWY HYDRO RELEASES 2025 COMMUNITY BENEFITS REPORT
Snowy Hydro has today released its first Snowy Mountains community benefits report, highlighting the organisation’s broad contribution to communities and economies across the region it calls home. The post SNOWY HYDRO RELEASES 2025 COMMUNITY BENEFITS REPORT appeared first on…